 |
| Back to Contents - Back
to Introduction |
| |
South Holland Local Plan - Adopted July 2006 |
Page 132 |
| |
| Appendix 1 |
| HOUSING LAND |
| |
|
| This appendix summarises the housing land situation as at 1 April 2004. A more detailed breakdown of the information is provided within the Local Plan Monitoring Report and Revised Urban Capacity Study, both of which are background papers to the Local Plan. |
| One of the key responsibilities of the Council is to ensure that there is sufficient housing land to meet the requirements of the District over the period of the Local Plan, 2001-2021. The plan aims to focus the majority of development in urban areas and to conform generally with the strategic housing requirement of the Lincolnshire Structure Plan for the period 2001-2021. The Structure Plan allocates 7600 dwellings to be distributed 5700 (75%) dwellings to the urban areas, namely the 5 towns, and 1900 (25%) to the rural areas as shown by Table 1. |
| The Housing Chapter explains how the new plan proposes to control development further by limiting where new planning permissions will be granted. In order to address the strategic housing aims for the District the plan aims to direct the majority of housing development towards the Main Town of Spalding. However the policies also aim to bring forward some new development in the Area Centres, namely the other four towns, namely Crowland, Holbeach, Long Sutton and Sutton Bridge and the main village of Donington. Given the sustainable development objectives of the plan, and the constraints on overall housing numbers the spatial strategy does not provide for major growth of the smaller villages. |
| The effect of the measures set out in the Housing Chapter is that the amount of new housing supply conforms to that required by the Structure Plan. |
| |
| Table 1: Structure Plan strategic housing provision |
| Location |
Emerging Structure plan
requirement 2001-2021 |
Per annum |
% |
| Urban Areas (5 towns) |
5700 |
285 |
75 |
| Rural Areas |
1900 |
95 |
25 |
| District Total |
7600 |
380 |
100 |
|
| |
| Table 2 reveals the housing land availability situation and shows the number of properties under construction and those not started as at 1 April 2004. Completions are also shown from the base date of the plan, 1 April 2001 up to 1 April 2004. The table identifies that there is still a higher level of development in the rural areas than that which policy allows for in the Structure Plan. However the policies in the Local Plan have helped bring the distribution of development more in line with the spatial strategy and housing provision set out in the Structure Plan since 2001. The proportion of housing in rural areas is 31%, and this is getting closer to the figure in the newly emerging Structure Plan, 25%. The proportion in the towns is getting correspondingly higher, closer to the 75% in the Structure Plan. |
| |
South Holland Local Plan - Adopted July 2006 |
Page 133 |
| |
| Table 2: Housing Land Availability as at 1 April 2004 |
| |
(a)Under Construction |
(b)Permission Not Started |
(c)Subtotal(a+b) |
(d)Completions 1 April 01-31 March 04 |
(e)Total(c+d) |
| |
Nos |
% |
Nos |
% |
Nos |
% |
Nos |
% |
Nos |
% |
| Urban Areas (5 towns) |
204 |
46 |
1965 |
86 |
2169 |
79 |
1093 |
55 |
3262 |
69 |
| (of which Spalding) |
(140) |
(31) |
(1367) |
(59) |
(1507) |
(55) |
(629) |
(32) |
(2136) |
(45) |
| Rural Areas |
242 |
54 |
333 |
14 |
575 |
21 |
883 |
45 |
1458 |
31 |
| District Total |
446 |
100 |
2298 |
100 |
2744 |
100 |
1976 |
100 |
4720 |
100 |
|
| |
| The Urban Capacity Study theoretically identified a significant amount of potential development that could occur through making more intensive use of land in residential areas. The Urban Capacity Study also revealed that with the exception of Spalding there is a limited range of unconstrained/modestly constrained brownfield sites available. The findings revealed that some greenfield land within the urban areas or urban extensions would also need to be identified to enable the Council to adequately meet the Regional Planning Guidance and Structure Plan strategic requirement to 2021, as shown by table 5. Table 3 identifies the urban capacity totals as at 1 April 2004. These capacity figures are also shown in tables 5 and 6. |
| |
| Table 3: Urban Capacity update 01 April 04 |
| Settlement |
Total Capacity |
Greenfield |
Brownfield |
| Total |
% |
Total |
% |
| Spalding |
448 |
76 |
17 |
372 |
83 |
| Crowland |
132 |
32 |
24 |
100 |
76 |
| Holbeach |
186 |
30 |
16 |
156 |
84 |
| Long Sutton |
138 |
40 |
29 |
98 |
71 |
| Sutton Bridge |
60 |
9 |
15 |
51 |
85 |
| Donington |
112 |
30 |
27 |
82 |
73 |
| Total |
1076 |
217 |
20 |
859 |
80 |
|
| |
| Table 4 sets out the Remaining Strategic Requirement for the District to 2021. Tables 5 and 6 identify specific plan provision in the urban and rural areas, based upon the remaining requirement from Table 4, namely 2438 in the urban areas and 442 in the rural areas. The plan’s provisions aim to ensure that the distribution of development is brought in line with the Structure Plan. |
| |
| Table 4: Remaining Strategic Requirement |
| |
Strategic
Requirement |
Total |
Remaining
Requirement |
| Urban Areas |
5700 |
3262 |
2438 |
| Rural Areas |
1900 |
1458 |
442 |
| Total |
7600 |
4720 |
2880 |
|
| |
South Holland Local Plan - Adopted July 2006 |
Page 134 |
| |
| Table 5: Strategic Requirement Breakdown in the Urban Areas |
Urban Areas
Remaining requirement
2438 |
|
| Spalding |
Capacity |
|
448 |
|
Allocations |
Holland Park- allocated previously |
450 |
|
|
Holland Park- additional extension |
1000 |
|
| Holbeach |
Capacity |
|
186 |
|
Allocations |
Land by A151 |
150 |
|
|
Foxes Lowe Road |
150 |
|
| Long Sutton |
Capacity |
|
138 |
|
Allocations |
Lime Walk |
80 |
|
| Crowland |
Capacity |
|
132 |
|
| Sutton Bridge |
Capacity |
|
60 |
|
Allocations |
Deallocation land at Bridge Road |
-290* |
|
|
Chestnut Terrace |
15 |
|
|
Withington Street |
15 |
|
|
Urban Total of plan provisions |
2534 |
|
| * Based upon the likely refusal of two renewal applications for approximately 290 dwellings in Sutton Bridge. |
| |
| Table 6: Strategic Requirement Breakdown in the Rural Areas |
Rural Areas
Remaining requirement
442
|
|
Donington |
Capacity |
112 |
|
Group Centres |
Brownfield/Infill Allowance |
200 |
|
Other Rural settlements |
Allowance |
80 |
|
Other open countryside |
Allowance |
40 |
|
|
Rural Total of plan provisions |
432 |
|
| |
| |
 |
 |
 |
 |
 |
| top |